Toronto permits multiplexes as-of-right on most residential lots, so many projects need no planning approval beyond a building permit. But the permission to build the use does not waive the zone’s standards. If your design is a little over on coverage, a little short on a setback, or a few centimetres too tall, you may need a minor variance from the Committee of Adjustment.

What the Committee of Adjustment is

The Committee of Adjustment is the local tribunal that decides minor-variance and consent (severance) applications. It holds public hearings, takes comments from neighbours and the City, and issues a decision.

The four tests under the Planning Act

  • The variance maintains the general intent and purpose of the Official Plan.
  • It maintains the general intent and purpose of the zoning by-law.
  • It is desirable for the appropriate development or use of the land.
  • It is minor in nature.

All four must be met. “Minor” is judged by impact, not just size: a small number can still be a big deal if it affects neighbours, and a larger number can be minor if it has no real effect.

Common multiplex variances

  • Side or rear setbacks on narrow or shallow lots.
  • Building depth or height by a small margin.
  • Lot coverage or landscaping where a design needs more area.
  • Projections, stairs and entrances.

Timeline and process

From submission to a decision, an application typically takes a matter of a few months, followed by an appeal period (appeals to the Ontario Land Tribunal are generally due within 20 days of the decision). That time needs to be in the project schedule. Construction cannot start on the varied elements until the variance is final.

How to avoid needing one

Test every standard during feasibility, before drawings are finished, and design to comply wherever it costs little to do so. Where a variance is worth having — because it adds a unit or materially improves the layout — plan it deliberately, with a short list of small, well-supported requests. Large asks dressed up as minor ones are the ones that get refused or appealed.

What’s changing

Recent reporting notes that the City has been reviewing how variances are evaluated and that policy changes are expanding what is permitted without planning approval. Rules and practice change, so we check the current position when we scope your project.

This article is general information, not legal or planning advice. Whether you need a variance depends on your lot and design.